Project name: Taiwan High Speed Rail Embankment Improvement Monitoring Project

Project location: THSR TK122+600 - TK122+700

Start time:

Complete time: June 2015

Project description:

Project details:

Due to the soil condition, a section of TK122 + 600 to TK122 + 700 Embankment of High-speed railways will be grouted and improved. During the construction period, in order to guarantee the safety of the train operation as well as the safety of adjacent construction, the automatic real-time monitoring system is adopted. Following the safety requirements, the alarm value can be set so that the system can automatically notify respective units when danger is detected.

Several instruments is installed in different locations, for example Optical Differential Settlement Monitoring System (ODSM) for monitor the stable and continuous long-term monitoring of differential settlement, and Advanced in Place Inclinometer (SAA) for monitor.


Main contractor: Taiwan High Speed Rail Corporation.


 

Copyright © 2018 Geotech Science. All Rights Reserved Website được thiết kế bởi Tất Thành