Project name: Singapore LTA Down Town Line(DTL) Stage 1-C9118B

Project location: Singapore

Start time: April 2008

Complete time:

Project description:

Project details:

SMRT is one of the important transportation systems in Singapore. Currently, there are three major lines: North-south line, East-west line and North-east line total length of 138KM. In coping with the rapid growth of population and industrial development, the Singapore government has planned and constructed another two lines, i.e. circle line and downtown line gradually.
  • This project is the stage 1 downtown line. The main contract is C9118B with three sub-contracts – C901, C906 and C907
  • The proposed construction MRT line related to the surrounding area are ORQ Building, Existing CST, MRT-NSL and IR construction site etc.
  • Providing fully automatic online real-time monitoring system with GPRS wireless transmission and solar panel power supply system.
  • Upon client’s request, alarm SMS and alarm e-mail system can be pre-setted with two to four alert level and work suspension level. In addition to these, upon different work nature of end users, it can be pre-set as receiving a certain degree of warning information (such as the higher level management can receive a higher warning as work suspension level).
  • For the sake of convenience for end users, whenever the result of the monitoring breaches alert level and work suspension level, SMS will be sent out automatically every 2 to 4 hours to inform the result of that particular instrument.
Main Contractor:Singapore Land Transport Authority (LTA).
Real-Time Monitoring System ( GeoAuto Software –Develop by GeoTech Co.).